A general contractor receives a change order request that will add $45,000 to the contract price and extend the schedule by 12 days. The original contract was for $850,000 with a 180-day duration. What percentage increase does this represent to the original contract value?
Correct Answer
A) 5.29%
The percentage increase is calculated as ($45,000 ÷ $850,000) × 100 = 5.29%. This represents the proportional increase in contract value due to the change order.
Why This Is the Correct Answer
Option A is correct because percentage increase is calculated by dividing the change amount by the original amount and multiplying by 100. The formula is: (Change Amount ÷ Original Amount) × 100 = Percentage Increase. In this case: ($45,000 ÷ $850,000) × 100 = 0.0529 × 100 = 5.29%. This is a fundamental percentage calculation that contractors must understand for change order analysis.
Why the Other Options Are Wrong
Option B: 4.85%
This answer (4.85%) is incorrect because it appears to be the result of an error in the division calculation or possibly confusing the numerator and denominator in the percentage formula.
Option C: 6.67%
This answer (6.67%) is significantly higher than the correct calculation and likely results from mathematical error or possibly using an incorrect base amount in the calculation.
Option D: 5.88%
This answer (5.88%) is close to the correct answer but represents a calculation error, possibly from rounding too early in the process or using incorrect figures.
Memory Technique
Remember 'CEO' - Change over Original equals percentage. The change order goes on top, original contract on bottom, then multiply by 100 for percentage.
Reference Hint
Look up contract administration and change order procedures in your Florida Building Code or construction management reference materials, typically found in project management chapters.
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass