EstatePass
Contract AdminContractseasy40% of exam part

A general contractor receives a change order request that will add $25,000 to the project cost and 10 days to the schedule. Before proceeding, the contractor must:

Correct Answer

A) Obtain written approval from the owner before starting the work

Change orders should be properly documented and approved in writing before work begins to avoid disputes over scope, cost, and time adjustments. This protects both the contractor and owner.

Answer Options
A
Obtain written approval from the owner before starting the work
B
Immediately begin the additional work
C
Complete the work and bill it as an extra
D
Refuse the change order to avoid delays

Why This Is the Correct Answer

Option B is correct because proper change order procedures require written documentation and owner approval before any additional work begins. This protects both parties by clearly establishing the scope, cost, and time implications of the change. Without written approval, contractors risk not being paid for extra work or facing disputes over what was actually authorized. Florida construction law and standard industry practices emphasize the importance of documented change orders to avoid costly litigation.

Why the Other Options Are Wrong

Option B: Immediately begin the additional work

Automatically refusing change orders is poor business practice and may violate contractual obligations to consider reasonable changes requested by the owner.

Option C: Complete the work and bill it as an extra

Completing work first and billing as an extra afterward puts the contractor at significant financial risk, as there's no guarantee the owner will pay for work that wasn't pre-approved in writing.

Memory Technique

Use the acronym 'WRITE' - Written approval Required before Initial Task Execution

Reference Hint

Florida Building Code Chapter 1, Section 105 - Construction Documents and Chapter 489 Florida Statutes regarding contractor licensing and change order requirements

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.