A general contractor receives a change order request that will add $25,000 to the project cost and 10 days to the schedule. Before proceeding, the contractor must:
Correct Answer
B) Obtain written approval from the owner before starting the work
Change orders should be properly documented and approved in writing before work begins to avoid disputes over scope, cost, and time adjustments. This protects both the contractor and owner.
Why This Is the Correct Answer
Option B is correct because proper change order procedures require written documentation and owner approval before any additional work begins. This protects both parties by clearly establishing the scope, cost, and time implications of the change. Without written approval, contractors risk not being paid for extra work or facing disputes over what was actually authorized. Florida construction law and standard industry practices emphasize the importance of documented change orders to avoid costly litigation.
Why the Other Options Are Wrong
Option A: Immediately begin the additional work
Starting work immediately without written approval is dangerous and can lead to payment disputes, as the contractor has no legal protection if the owner later refuses to pay for unauthorized work.
Option C: Complete the work and bill it as an extra
Completing work first and billing as an extra afterward puts the contractor at significant financial risk, as there's no guarantee the owner will pay for work that wasn't pre-approved in writing.
Option D: Refuse the change order to avoid delays
Automatically refusing change orders is poor business practice and may violate contractual obligations to consider reasonable changes requested by the owner.
Memory Technique
Use the acronym 'WRITE' - Written approval Required before Initial Task Execution
Reference Hint
Florida Building Code Chapter 1, Section 105 - Construction Documents and Chapter 489 Florida Statutes regarding contractor licensing and change order requirements
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
A building permit fee calculation includes a base fee of $125 plus $0.75 per square foot for a 4,200 square foot residence. Additionally, there is a 3% processing fee on the total. What is the final permit cost?
Next Question
A project has activities A (5 days), B (3 days), and C (4 days). Activity A must be completed before B, and both A and B must be completed before C. What is the total project duration using CPM?