A general contractor is working on a public project with a contract value of $3.2 million. The performance bond amount is typically what percentage of the contract value?
Correct Answer
C) 100%
Performance bonds on public projects typically equal 100% of the contract value to ensure complete project performance.
Why This Is the Correct Answer
100% is correct. For public construction projects, the Miller Act (federal) and equivalent Little Miller Acts (state) require performance bonds equal to 100% of the contract value. This ensures that if the contractor defaults, the surety can fund completion of the entire project. A 100% bond on a $3.2 million contract means a $3.2 million bond.
Why the Other Options Are Wrong
Option A: 110%
110% is incorrect. No standard bond requirement exceeds 100% of the contract value. A bond greater than the contract amount is not used in standard practice because the bond covers the cost of completing the work, which is bounded by the original contract value.
Option B: 50%
50% is incorrect. A 50% bond is sometimes used on private projects with modified risk tolerance, but it does not provide adequate protection for public projects. The Miller Act mandates 100% for federal public work.
Option D: 75%
75% is incorrect. There is no standard that sets the performance bond at 75% of the contract value. This percentage would leave 25% of the project value uncovered in a default scenario.
Memory Technique
Public project + Performance Bond = 100%. Think of it as a FULL guarantee: the bond fully mirrors the contract. 'Public projects get full protection.' The math is simple: $3.2M contract Γ 100% = $3.2M bond.
More NASCLA Questions
How long should daily reports and project correspondence typically be retained after project completion?
Which AIA document contains the general conditions that govern the rights and responsibilities of all parties in a construction contract?
A construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?
What is the primary purpose of job cost accounting in construction?
A construction company has current assets of $350,000 and current liabilities of $280,000. What is the company's working capital?
In CSI MasterFormat, which division covers earthwork and site preparation?
On an electrical plan, a rectangle with three parallel lines inside typically represents:
In a mechanical drawing, what does 'CFM' typically measure?
In CSI MasterFormat Division 08, which of the following would typically be included?
On a mechanical plan, what does the symbol 'RTU' typically indicate?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
