A general contractor is working on a project that will impact 3.2 acres near a waterway. In addition to the NPDES Construction General Permit, what other federal permit may be required?

Correct Answer

B) Section 404 permit from the Army Corps of Engineers

Projects near waterways that may impact wetlands or waters of the United States require a Section 404 permit from the Army Corps of Engineers in addition to NPDES stormwater permits.

Answer Options
A
Clean Air Act permit
B
Section 404 permit from the Army Corps of Engineers
C
RCRA hazardous waste permit
D
TSCA chemical notification

Why This Is the Correct Answer

Section 404 permits from the Army Corps of Engineers are specifically required for any construction activities that involve dredging, filling, or otherwise impacting wetlands or waters of the United States. Since this project is near a waterway and covers 3.2 acres, there's a high likelihood of wetland impact. The Section 404 permit works in conjunction with NPDES permits to provide comprehensive water protection. This is a fundamental requirement under the Clean Water Act that general contractors must understand.

Why the Other Options Are Wrong

Option A: Clean Air Act permit

Clean Air Act permits are required for projects that emit air pollutants, not for construction near waterways. While construction projects may generate dust and emissions, the question specifically focuses on waterway proximity, making air quality permits irrelevant to this scenario.

Option C: RCRA hazardous waste permit

RCRA hazardous waste permits are only required when a project involves the treatment, storage, or disposal of hazardous waste. Standard construction projects near waterways do not automatically trigger RCRA permitting requirements unless hazardous materials are specifically involved.

Option D: TSCA chemical notification

TSCA chemical notifications are required for the manufacture, import, or use of certain chemical substances, not for construction activities near waterways. This permit type is unrelated to construction projects and water protection requirements.

Memory Technique

Think '404 Water Error' - just like a 404 web error stops you from proceeding, you can't proceed with waterway construction without a Section 404 permit from the Army Corps of Engineers.

Reference Hint

Environmental regulations chapter, specifically Clean Water Act requirements and Army Corps of Engineers permitting sections

More Business & Finance Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing