A general contractor discovers that the mechanical subcontractor installed ductwork 6 inches lower than shown on the approved shop drawings, creating a conflict with the electrical conduit. This situation should be addressed through:
Correct Answer
A) A coordination meeting with affected trades
This field coordination issue requires immediate attention through a coordination meeting with the mechanical and electrical trades to develop a solution. The GC needs to facilitate resolution between the trades while considering schedule and cost impacts.
Why This Is the Correct Answer
A coordination meeting is the most appropriate immediate response to resolve field conflicts between trades. The general contractor must facilitate communication between the mechanical and electrical subcontractors to develop a practical solution that addresses the ductwork/conduit conflict. This approach allows for collaborative problem-solving, considers multiple resolution options, evaluates cost and schedule impacts, and maintains project momentum while ensuring proper coordination between affected trades.
Why the Other Options Are Wrong
Option B: An immediate stop work order for all trades
A stop work order for all trades is excessive and costly for a localized coordination issue. This would halt the entire project unnecessarily when the conflict only affects specific mechanical and electrical work areas. The general contractor should first attempt resolution through coordination meetings before considering such drastic measures that impact schedule and budget.
Option C: A change order to raise the ceiling height
A change order to raise the ceiling height is premature and potentially unnecessary. This assumes a specific solution without first exploring alternatives through coordination. The trades may be able to resolve the conflict through rerouting, repositioning, or other field adjustments that don't require expensive structural changes or formal change orders.
Option D: A request for information (RFI) to the architect
An RFI to the architect is inappropriate because this is a field coordination issue, not a design clarification matter. The approved shop drawings were clear; the problem is improper installation by the mechanical contractor. The general contractor should resolve this through trade coordination rather than involving the design team unnecessarily.
Memory Technique
Remember 'COORDINATE before you ESCALATE' - field conflicts between trades should first be addressed through coordination meetings before involving designers or issuing change orders.
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
