A crew of 6 workers can install 240 linear feet of electrical conduit in 8 hours. If you need to install 900 linear feet and want to complete the work in 6 hours, how many workers do you need?
Correct Answer
C) 15 workers
Current rate: 240 LF ÷ (6 workers × 8 hours) = 5 LF per worker-hour. For 900 LF in 6 hours: 900 ÷ 6 = 150 LF per hour needed. 150 LF ÷ 5 LF per worker-hour = 30 worker-hours ÷ 6 hours = 5 workers per hour × 3 shifts = 15 workers.
Why This Is the Correct Answer
First, calculate the productivity rate: 240 LF ÷ (6 workers × 8 hours) = 5 LF per worker-hour. To install 900 LF in 6 hours requires 900 ÷ 6 = 150 LF per hour. Since each worker produces 5 LF per hour, you need 150 ÷ 5 = 30 worker-hours per hour, which means 15 workers working simultaneously for 6 hours.
Why the Other Options Are Wrong
Option A: 18 workers
18 workers would provide 18 × 5 = 90 LF per hour × 6 hours = 540 LF total, which is insufficient to complete the 900 LF required. This answer likely comes from miscalculating the required production rate or worker productivity.
Option B: 12 workers
12 workers would produce 12 × 5 = 60 LF per hour × 6 hours = 360 LF total, falling far short of the 900 LF requirement. This error typically results from incorrect unit conversions or misunderstanding the time constraint.
Option D: 20 workers
20 workers would produce 20 × 5 = 100 LF per hour × 6 hours = 600 LF total, which is still 300 LF short of the 900 LF target. This represents overestimating workforce needs without proper calculation verification.
Memory Technique
Remember 'Rate × Workers × Time = Total Work.' First find the rate per worker-hour, then work backwards from your target (900 LF in 6 hours) to find required workers.
More NASCLA Questions
Which AIA document contains the general conditions that govern the rights and responsibilities of all parties in a construction contract?
A construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?
What is the primary purpose of job cost accounting in construction?
A construction company has current assets of $350,000 and current liabilities of $280,000. What is the company's working capital?
In CSI MasterFormat, which division covers earthwork and site preparation?
In a mechanical drawing, what does 'CFM' typically measure?
In CSI MasterFormat Division 08, which of the following would typically be included?
On a mechanical plan, what does the symbol 'RTU' typically indicate?
What is the minimum preheat temperature for welding ASTM A992 steel when the ambient temperature is 15°F?
A general contractor's balance sheet shows total assets of $850,000, current liabilities of $320,000, and long-term debt of $180,000. What is the company's equity?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
A specification calls for materials to comply with ASTM standards. Under which CSI MasterFormat division would you typically find detailed ASTM requirements for structural steel?
Next Question
Which type of insurance provides coverage for employees who are injured while performing their job duties?
