A contractor's project has actual costs of $85,000 against a budget of $90,000 and is 75% complete. What is the projected final cost using the cost-to-complete method?
Correct Answer
B) $113,333
If 75% complete with $85,000 spent, the projected final cost is $85,000 ÷ 0.75 = $113,333. This indicates a potential cost overrun.
Why This Is the Correct Answer
The cost-to-complete method projects final cost by dividing actual costs spent by the percentage of work completed. With $85,000 spent at 75% completion, the calculation is $85,000 ÷ 0.75 = $113,333. This method assumes the remaining work will continue at the same cost efficiency rate as the work completed so far. The result shows a significant cost overrun from the original $90,000 budget.
Why the Other Options Are Wrong
Option A: $90,000
This is the original budget amount, not the projected final cost based on current spending patterns. Using the original budget ignores the actual cost performance data.
Option C: $95,000
This amount is too low and doesn't reflect the actual spending rate. It appears to be an arbitrary adjustment to the original budget rather than a calculation based on actual performance.
Option D: $106,667
This amount results from an incorrect calculation method. It may come from adding remaining budget to actual costs spent, which is not the proper cost-to-complete methodology.
Memory Technique
Think 'Spent over Done' - divide what you've Spent by what percentage is Done to get your projected total cost
Reference Hint
Project Management chapter, specifically sections on cost control, earned value management, and project cost forecasting methods
More Business & Finance Questions
A contractor's license expires on March 31st. If they submit a renewal application on April 15th, what additional requirement must be met under Florida regulations?
A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?
In Florida, what is the minimum workers' compensation insurance coverage required for construction companies with employees?
What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?
A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?