EstatePass
Contract AdminContractsmedium40% of exam part

A contractor's cost-plus contract has a fee of 8% and actual project costs of $750,000. If there was a $50,000 cost overrun due to owner-requested changes, what is the contractor's total fee?

Correct Answer

B) $64,000

The contractor's fee is calculated on total allowable costs including approved changes. Total costs are $750,000 + $50,000 = $800,000. Fee = $800,000 × 0.08 = $64,000.

Answer Options
A
$60,000
B
$64,000
C
$66,000
D
$68,000

Why This Is the Correct Answer

In a cost-plus contract, the contractor's fee is calculated as a percentage of the total allowable project costs, which includes both the original costs and any approved change orders. Since the $50,000 cost overrun was due to owner-requested changes, it becomes part of the allowable costs. The total allowable costs are $750,000 + $50,000 = $800,000, and the contractor's fee is 8% of this total, which equals $64,000.

Why the Other Options Are Wrong

Option A: $60,000

This calculates the fee only on the original project costs ($750,000 × 0.08 = $60,000) and incorrectly excludes the owner-requested changes from the fee calculation.

Option C: $66,000

This appears to add a flat amount to the base fee rather than calculating the percentage correctly on the total allowable costs.

Option D: $68,000

This incorrectly calculates the fee, possibly by adding the change order amount incorrectly or using wrong percentages in the calculation.

Memory Technique

Remember 'CAFE' - Cost-plus contracts include All Fees on Everything allowable (original costs + approved changes)

Reference Hint

Florida Building Construction Standards - Contract Types and Payment Methods chapter, specifically the section on Cost-Plus contracts and fee calculations

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing