A contractor's cost-plus contract has a fee of 8% and actual project costs of $750,000. If there was a $50,000 cost overrun due to owner-requested changes, what is the contractor's total fee?
Correct Answer
B) $64,000
The contractor's fee is calculated on total allowable costs including approved changes. Total costs are $750,000 + $50,000 = $800,000. Fee = $800,000 × 0.08 = $64,000.
Why This Is the Correct Answer
In a cost-plus contract, the contractor's fee is calculated as a percentage of the total allowable project costs, which includes both the original costs and any approved change orders. Since the $50,000 cost overrun was due to owner-requested changes, it becomes part of the allowable costs. The total allowable costs are $750,000 + $50,000 = $800,000, and the contractor's fee is 8% of this total, which equals $64,000.
Why the Other Options Are Wrong
Option A: $60,000
This calculates the fee only on the original project costs ($750,000 × 0.08 = $60,000) and incorrectly excludes the owner-requested changes from the fee calculation.
Option C: $66,000
This appears to add a flat amount to the base fee rather than calculating the percentage correctly on the total allowable costs.
Option D: $68,000
This incorrectly calculates the fee, possibly by adding the change order amount incorrectly or using wrong percentages in the calculation.
Memory Technique
Remember 'CAFE' - Cost-plus contracts include All Fees on Everything allowable (original costs + approved changes)
Reference Hint
Florida Building Construction Standards - Contract Types and Payment Methods chapter, specifically the section on Cost-Plus contracts and fee calculations
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass