A contractor submitted plans for a 12-unit apartment building. The plan review fee is $125 for the first unit plus $15 for each additional unit. What is the total plan review fee?
Correct Answer
C) $290
The calculation is: $125 (first unit) + ($15 × 11 additional units) = $125 + $165 = $290. This tiered fee structure is common in many Florida jurisdictions for multi-unit residential projects.
Why This Is the Correct Answer
The correct answer is A ($290) because this is a tiered fee calculation where the first unit costs $125 and each additional unit costs $15. With 12 total units, there are 11 additional units beyond the first. The calculation is $125 + (11 × $15) = $125 + $165 = $290. This type of progressive fee structure is standard in Florida municipal building departments to account for the base review cost plus incremental costs for additional units.
Why the Other Options Are Wrong
Option A: $305
Option D ($315) is incorrect and likely results from miscalculating the number of additional units or adding an extra fee. This could come from calculating $125 + (12 × $15) + some additional error, showing a fundamental misunderstanding of the tiered fee structure.
Option B: $315
Option C ($180) is incorrect because it only calculates 12 × $15 = $180, completely ignoring the base fee structure. This fails to account for the fact that the first unit has a different fee ($125) than the additional units ($15 each).
Memory Technique
Remember 'First is Special' - in tiered fee structures, the first unit always has a special (usually higher) rate, then count carefully: Total units MINUS 1 equals additional units for the lower rate.
Reference Hint
Florida Building Code, Administrative Chapter, Section on Permit Fees and Fee Schedules - typically found in local building department fee ordinances
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?