A contractor submits a payment application for $180,000. The owner approves $165,000, citing deficient work worth $15,000. Under AIA A201, what options does the contractor have?

Correct Answer

A) Accept the partial payment and continue with dispute resolution for the remainder

Under AIA A201, contractors should generally accept partial payments for undisputed amounts and pursue dispute resolution procedures for contested portions while continuing work.

Answer Options
A
Accept the partial payment and continue with dispute resolution for the remainder
B
Stop work immediately until full payment is received
C
Terminate the contract for non-payment
D
Automatically file a mechanics lien for the disputed amount

Why This Is the Correct Answer

Under AIA A201, contractors should generally accept partial payments for undisputed amounts and pursue dispute resolution procedures for contested portions while continuing work.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.