A contractor receives a change order directive to proceed with additional work valued at $150,000 while the change order cost is still being negotiated. What should the contractor do?
Correct Answer
C) Proceed with the work and document costs for later negotiation
A change order directive typically requires the contractor to proceed with the work while cost negotiations continue. The contractor should document all costs and time impacts for later negotiation and adjustment.
Why This Is the Correct Answer
A change order directive typically requires the contractor to proceed with the work while cost negotiations continue. The contractor should document all costs and time impacts for later negotiation and adjustment.
More NASCLA Questions
Which AIA document contains the general conditions that govern the rights and responsibilities of all parties in a construction contract?
A construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?
What is the primary purpose of job cost accounting in construction?
A construction company has current assets of $350,000 and current liabilities of $280,000. What is the company's working capital?
In CSI MasterFormat, which division covers earthwork and site preparation?
In a mechanical drawing, what does 'CFM' typically measure?
In CSI MasterFormat Division 08, which of the following would typically be included?
On a mechanical plan, what does the symbol 'RTU' typically indicate?
What is the minimum preheat temperature for welding ASTM A992 steel when the ambient temperature is 15Β°F?
A general contractor's balance sheet shows total assets of $850,000, current liabilities of $320,000, and long-term debt of $180,000. What is the company's equity?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
