EstatePass
NASCLAContractsmedium15% of exam part

A contractor receives a change order directive to proceed with additional work valued at $150,000 while the change order cost is still being negotiated. What should the contractor do?

Correct Answer

C) Proceed with the work and document costs for later negotiation

A change order directive typically requires the contractor to proceed with the work while cost negotiations continue. The contractor should document all costs and time impacts for later negotiation and adjustment.

Answer Options
A
Proceed only if paid in advance
B
Submit the work to arbitration
C
Proceed with the work and document costs for later negotiation
D
Refuse to proceed until the cost is agreed upon

Why This Is the Correct Answer

A change order directive typically requires the contractor to proceed with the work while cost negotiations continue. The contractor should document all costs and time impacts for later negotiation and adjustment.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.