EstatePass
Project MgmtBlueprintseasy17% of exam part

A contractor notices a discrepancy between the architectural drawings and structural drawings regarding beam sizes. What should be the first course of action?

Correct Answer

C) Submit a Request for Information (RFI) to the design team

When discrepancies exist between drawings, the contractor should submit an RFI to clarify the conflict rather than making assumptions. This protects all parties and ensures proper design intent.

Answer Options
A
Use the larger beam size shown on either drawing
B
Follow the architectural drawings since they were issued first
C
Submit a Request for Information (RFI) to the design team
D
Use engineering judgment to select the appropriate beam

Why This Is the Correct Answer

Submitting an RFI is the proper protocol when discrepancies exist between contract documents. This formal process ensures the design team can clarify their intent and provide written direction. Making assumptions about beam sizes could lead to structural inadequacy or costly over-engineering, and the contractor would bear liability for any incorrect decisions. The RFI process protects all parties by documenting the issue and obtaining official clarification.

Why the Other Options Are Wrong

Option A: Use the larger beam size shown on either drawing

Simply choosing the larger beam size is an assumption that could lead to unnecessary costs and may not address the actual design intent. The larger beam might not be structurally appropriate for the specific application, and this approach bypasses proper communication protocols.

Option B: Follow the architectural drawings since they were issued first

The order in which drawings were issued does not determine precedence when there are conflicts. Architectural drawings and structural drawings serve different purposes, and structural elements should be verified through proper channels rather than assumed based on issue dates.

Option D: Use engineering judgment to select the appropriate beam

Contractors should not use their own engineering judgment to resolve conflicts between design documents unless they are licensed engineers and have been contracted to provide design services. This approach assumes liability that belongs to the design team and could violate licensing requirements.

Memory Technique

RFI = 'Resolve First, Install' - always resolve discrepancies before proceeding with installation

Reference Hint

Florida Building Code, Chapter 1 - Administration and Enforcement, sections on construction documents and approved plans

More Project Mgmt Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing