A contractor needs to obtain permits for a $750,000 commercial renovation. The permit fees include: Building permit ($5,200), Electrical permit ($850), Plumbing permit ($650), and Mechanical permit ($1,100). What is the total permit cost as a percentage of project value?
Correct Answer
C) 1.04%
Total permit costs: $5,200 + $850 + $650 + $1,100 = $7,800. Percentage of project value: ($7,800 ÷ $750,000) × 100 = 1.04%.
Why This Is the Correct Answer
Option B is correct because it accurately calculates the total permit costs and converts them to a percentage of project value. The calculation involves adding all four permit fees ($5,200 + $850 + $650 + $1,100 = $7,800), then dividing by the project value ($750,000) and multiplying by 100. This yields exactly 1.04%, which represents the proper relationship between permit costs and total project investment.
Why the Other Options Are Wrong
Option A: 0.89%
Option A (0.89%) is incorrect because it underestimates the percentage. This could result from either miscalculating the total permit fees or making an error in the division/percentage conversion process.
Option B: 1.15%
Option D (1.28%) is incorrect because it significantly overestimates the percentage. This could result from either inflating the total permit costs or errors in the mathematical conversion to percentage form.
Memory Technique
Remember 'BEPM' for the four main permit types: Building, Electrical, Plumbing, Mechanical. Typical permit costs run 1-2% of project value for commercial work.
Reference Hint
Florida Building Code Administrative Chapter, Section on Permit Fees and Fee Schedules
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?