A contractor needs to install a tile roof on a building with a roof slope of 3:12. What is the minimum underlayment requirement for this application in Florida?
Correct Answer
C) Double layer of #15 felt
For tile roofs with slopes between 2.5:12 and 4:12, the Florida Building Code requires double layer underlayment to provide adequate weather protection due to the lower slope.
Why This Is the Correct Answer
CORRECT_ANSWER - For tile roofs with slopes between 2.5:12 and 4:12, the Florida Building Code requires double layer underlayment because the lower slope creates greater risk of water infiltration. A 3:12 slope falls within this range where single layer protection is insufficient. The double layer provides redundant protection against wind-driven rain that can penetrate under tiles on lower-sloped roofs.
Why the Other Options Are Wrong
Option A: Single layer of #15 felt
Single layer of #15 felt is insufficient for tile roofs at 3:12 slope. This minimal underlayment doesn't provide adequate protection against water infiltration that can occur with lower slope tile installations.
Option B: Single layer of #30 felt
While #30 felt is heavier than #15 felt, a single layer still doesn't meet the Florida Building Code requirement for tile roofs at 3:12 slope. The code specifically requires double layer protection in this slope range.
Option D: Self-adhering membrane
Self-adhering membrane is typically used for ice dam protection in cold climates or special waterproofing applications, but it's not the standard requirement for tile roofs at 3:12 slope in Florida. The code specifies double layer felt underlayment for this application.
Memory Technique
Remember '3 in the middle needs double' - a 3:12 slope is in the middle range (2.5-4) that requires double layer protection
Reference Hint
Florida Building Code Chapter 15 - Roof Assemblies and Rooftop Structures, specifically the section on underlayment requirements for tile roofing systems
More Project Mgmt Questions
What is the minimum R-value required for wall insulation in Florida Climate Zone 2?
A subcontractor brings a new chemical product to your jobsite. Under the Globally Harmonized System (GHS), what information must be immediately available to workers?
A construction site has a trench that is 8 feet deep in Type B soil. What is the maximum allowable slope ratio for the trench walls without protective systems?
A detail drawing shows a scale of 3/4" = 1'-0". If a dimension measures 2.25 inches on the drawing, what is the actual dimension?
What is the maximum recommended spacing between drywall screws when attaching to wood studs?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass