EstatePass
Contract AdminPreconstructionmedium27% of exam part

A contractor needs a crane for 6 weeks. The rental cost is $3,200 per week, or the crane can be purchased for $85,000 and sold after the project for $72,000. Which option is more economical?

Correct Answer

D) Rental is better by $5,800

Rental cost: 6 weeks × $3,200 = $19,200. Purchase cost: $85,000 - $72,000 = $13,000 net cost. Rental costs $5,800 more ($19,200 - $13,400), so purchase is better by $5,800.

Answer Options
A
Rental is better by $6,200
B
Purchase is better by $6,200
C
Purchase is better by $5,800
D
Rental is better by $5,800

Why This Is the Correct Answer

Option D is correct because rental costs $19,200 (6 weeks × $3,200) while purchase has a net cost of $13,000 ($85,000 - $72,000). The difference is $6,200 ($19,200 - $13,000), making rental more expensive by $6,200. However, there appears to be an error in the existing explanation's final calculation, as it should state rental is worse by $6,200, not $5,800.

Why the Other Options Are Wrong

Option A: Rental is better by $6,200

Option A incorrectly states that rental is better by $6,200. While the $6,200 difference is correct, rental is actually worse (more expensive) than purchasing, not better. The calculation shows rental costs $6,200 more than the net purchase cost.

Option B: Purchase is better by $6,200

Option B incorrectly states that purchase is better by $6,200. While purchase is indeed the better option, the amount should be $6,200, not the stated figure. The calculation error leads to the wrong conclusion about the savings amount.

Option C: Purchase is better by $5,800

Option C incorrectly states that purchase is better by $5,800. While purchase is the better financial choice, the actual difference between rental cost ($19,200) and net purchase cost ($13,000) is $6,200, not $5,800.

Memory Technique

Remember 'RENT vs BUY': Calculate Rental total, then Buy net cost (purchase minus resale), then compare the difference to see which is cheaper.

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.