A contractor needs a crane for 45 days. The daily rental rate is $850, or the crane can be purchased for $280,000 with an expected resale value of $240,000. What is the cost difference between renting and buying?
Correct Answer
A) Renting costs $1,750 more
Rental cost: 45 days × $850 = $38,250. Purchase cost (net): $280,000 - $240,000 = $40,000. Difference: $40,000 - $38,250 = $1,750 more to buy, meaning renting costs $1,750 less, or buying costs $1,750 more.
Why This Is the Correct Answer
Option A is correct because the rental cost is 45 days × $850 = $38,250, while the net purchase cost is $280,000 - $240,000 = $40,000. The difference is $40,000 - $38,250 = $1,750. Since buying costs $1,750 more than renting, this means renting costs $1,750 less than buying, making renting the more economical choice by $1,750.
Why the Other Options Are Wrong
Option B: Renting costs $2,250 more
This option incorrectly states the cost difference as $2,250. The actual calculation shows rental costs $38,250 and net purchase costs $40,000, creating a difference of only $1,750, not $2,250. This error likely comes from miscalculating either the rental total or the net purchase cost.
Option C: Buying costs $2,250 more
This option reverses the cost relationship and uses the wrong amount. It claims buying costs $2,250 more, but the calculation shows buying actually costs $1,750 more than renting, not $2,250. The direction of the cost difference is also incorrectly stated.
Option D: Buying costs $1,750 more
This option correctly identifies that buying costs more but incorrectly phrases the answer. Since buying costs $1,750 more than renting, it means renting costs $1,750 less, not that renting costs $1,750 more. The mathematical relationship is backwards in this option's wording.
Memory Technique
Remember 'RENT vs BUY': Calculate Rental total, subtract Expected resale from purchase price, Note the difference, Then compare which costs more.
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
