EstatePass
Business & FinanceOperationsmedium10% of exam part

A contractor needs 500 cubic yards of concrete for a project starting in 6 weeks. The local supplier can only guarantee delivery of 300 cubic yards by the start date. What is the best procurement strategy?

Correct Answer

B) Secure the 300 cubic yards from the primary supplier and arrange for 200 cubic yards from a secondary supplier

The best strategy is to secure what you can from the reliable primary supplier and arrange for the balance from a secondary source. This ensures project schedule adherence while maintaining some supplier relationships.

Answer Options
A
Delay the project start by 2 weeks to get all concrete from one supplier
B
Secure the 300 cubic yards from the primary supplier and arrange for 200 cubic yards from a secondary supplier
C
Change the project design to use only 300 cubic yards of concrete
D
Order 500 cubic yards from a different supplier entirely

Why This Is the Correct Answer

Option B represents the most practical and professional procurement strategy that balances multiple project management priorities. It maintains the established relationship with the primary supplier while ensuring project schedule adherence by securing additional materials from a secondary source. This approach demonstrates good risk management by not putting all procurement eggs in one basket, while also showing flexibility and problem-solving skills that are essential in construction management.

Why the Other Options Are Wrong

Option A: Delay the project start by 2 weeks to get all concrete from one supplier

Delaying the project start creates a cascade of problems including potential contract penalties, schedule conflicts with other trades, increased labor costs, and possible client dissatisfaction. Project delays should be a last resort, not a first option when alternative procurement solutions exist.

Option C: Change the project design to use only 300 cubic yards of concrete

Changing project design to accommodate material shortages is typically not within the contractor's authority and would require extensive redesign, engineering approval, permit modifications, and client consent. This approach is costly, time-consuming, and may compromise the project's intended function.

Option D: Order 500 cubic yards from a different supplier entirely

Abandoning the primary supplier entirely for an untested supplier introduces significant risk regarding quality, reliability, and delivery guarantees. There's no assurance that a different supplier can deliver the full 500 cubic yards on time, and this approach burns bridges with the established supplier relationship.

Memory Technique

Think 'SPLIT to HIT' - Split your procurement to Hit your deadlines when facing material shortages

Reference Hint

Florida Building Code - Chapter 19 (Concrete) and Project Management sections dealing with material procurement and scheduling

More Business & Finance Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing