A contractor needs 250 cubic yards of concrete for a foundation. The concrete costs $120 per cubic yard delivered, and there is typically 3% waste. What is the total material cost including waste?
Correct Answer
B) $30,900
First add waste: 250 cubic yards × 1.03 = 257.5 cubic yards. Then multiply by cost: 257.5 × $120 = $30,900.
Why This Is the Correct Answer
Option B correctly accounts for both the base concrete quantity and the waste factor. The calculation properly multiplies the required 250 cubic yards by 1.03 (which represents 100% + 3% waste) to get 257.5 cubic yards. This adjusted quantity is then multiplied by the unit cost of $120 per cubic yard to arrive at the total material cost of $30,900.
Why the Other Options Are Wrong
Option A: $30,000
This answer fails to include the 3% waste factor, calculating only the base cost of 250 cubic yards × $120 = $30,000, which would leave the contractor short on materials.
Option C: $31,800
This answer incorrectly calculates waste by adding 3% to the final cost rather than to the quantity, or uses an incorrect waste percentage in the calculation.
Option D: $32,400
This answer applies an excessive waste factor, possibly calculating 250 × 1.08 × $120 or using another incorrect multiplier that results in overestimating the required materials.
Memory Technique
Remember 'QTY first, COST last' - always apply waste to Quantity first, then calculate the Cost. Think of waste as 'ordering extra material' not 'paying extra money.'
Reference Hint
Florida Building Code - Chapter on Concrete and Masonry, or Construction Estimating references covering material waste factors
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
A contractor receives a Notice to Owner from a subcontractor. Under Florida lien law, what action should the contractor take to protect themselves?
Next Question
According to Florida Statute Chapter 713, within how many days must a contractor serve a Notice to Owner after first providing labor or materials to the project?