EstatePass
Contract AdminPreconstructionmedium27% of exam part

A contractor needs 250 cubic yards of concrete for a foundation. The concrete costs $120 per cubic yard delivered, and there is typically 3% waste. What is the total material cost including waste?

Correct Answer

B) $30,900

First add waste: 250 cubic yards × 1.03 = 257.5 cubic yards. Then multiply by cost: 257.5 × $120 = $30,900.

Answer Options
A
$30,000
B
$30,900
C
$31,800
D
$32,400

Why This Is the Correct Answer

Option B correctly accounts for both the base concrete quantity and the waste factor. The calculation properly multiplies the required 250 cubic yards by 1.03 (which represents 100% + 3% waste) to get 257.5 cubic yards. This adjusted quantity is then multiplied by the unit cost of $120 per cubic yard to arrive at the total material cost of $30,900.

Why the Other Options Are Wrong

Option A: $30,000

This answer fails to include the 3% waste factor, calculating only the base cost of 250 cubic yards × $120 = $30,000, which would leave the contractor short on materials.

Option C: $31,800

This answer incorrectly calculates waste by adding 3% to the final cost rather than to the quantity, or uses an incorrect waste percentage in the calculation.

Option D: $32,400

This answer applies an excessive waste factor, possibly calculating 250 × 1.08 × $120 or using another incorrect multiplier that results in overestimating the required materials.

Memory Technique

Remember 'QTY first, COST last' - always apply waste to Quantity first, then calculate the Cost. Think of waste as 'ordering extra material' not 'paying extra money.'

Reference Hint

Florida Building Code - Chapter on Concrete and Masonry, or Construction Estimating references covering material waste factors

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing