Business & FinanceRegulationshard15% of exam part

A contractor is required to post a performance bond for 15% of contract value on a $1,850,000 project. If the bonding company charges a premium of 1.2% of the bond amount, what is the total bonding cost?

Correct Answer

D) $3,330

First calculate bond amount: $1,850,000 × 0.15 = $277,500. Then calculate premium: $277,500 × 0.012 = $3,330. Performance bonds are typically a percentage of contract value.

Answer Options
A
$3,730
B
$3,630
C
$3,530
D
$3,330

Why This Is the Correct Answer

The correct answer follows a two-step calculation process. First, the bond amount is calculated as 15% of the contract value: $1,850,000 × 0.15 = $277,500. Then, the bonding premium is calculated as 1.2% of the bond amount: $277,500 × 0.012 = $3,330. This represents the total cost the contractor must pay to the bonding company for the performance bond.

Why the Other Options Are Wrong

Option A: $3,730

This answer likely results from calculation errors, possibly using incorrect percentages or rounding mistakes in the multi-step calculation process.

Option B: $3,630

This answer suggests an error in either the bond amount calculation or the premium calculation, possibly from using wrong decimal conversions or mathematical mistakes.

Option C: $3,530

This answer indicates significant calculation errors, possibly from incorrectly applying the percentages or making arithmetic mistakes in the two-step process.

Memory Technique

Remember 'Contract to Bond to Premium' - it's always a two-step multiplication: Contract Value × Bond % = Bond Amount, then Bond Amount × Premium % = Total Cost.

Reference Hint

Look up 'Performance Bonds' and 'Contract Security' sections in Florida Construction Law or Business and Finance chapters of exam reference materials.

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.