EstatePass
Contract AdminProcedureshard13% of exam part

A contractor is pursuing LEED points for regional materials. The project is located in Miami, and a supplier offers materials manufactured 450 miles away in Atlanta. Do these materials qualify for LEED regional materials credit?

Correct Answer

B) Yes, because they are within the 500-mile radius requirement

LEED regional materials credit requires materials to be extracted, harvested, or recovered, as well as manufactured within 500 miles of the project site. At 450 miles, these materials qualify.

Answer Options
A
No, because they exceed the 500-mile radius requirement
B
Yes, because they are within the 500-mile radius requirement
C
Yes, because they are from the same region
D
No, because they must be manufactured within the same state

Why This Is the Correct Answer

LEED regional materials credit requires that materials be extracted, harvested, or recovered AND manufactured within a 500-mile radius of the project site. Since the materials from Atlanta are manufactured 450 miles from Miami, they fall within the 500-mile requirement. This distance criterion helps reduce transportation impacts and supports the local economy, which are key goals of the LEED regional materials credit.

Why the Other Options Are Wrong

Option A: No, because they exceed the 500-mile radius requirement

While Atlanta and Miami could be considered part of the same southeastern region geographically, LEED doesn't use vague regional boundaries for this credit. The requirement is specifically distance-based (500-mile radius), not based on general geographic regions or cultural areas.

Option C: Yes, because they are from the same region

This option incorrectly states that 450 miles exceeds the 500-mile requirement. Since 450 is less than 500, the materials actually meet the distance requirement and would qualify for the credit.

Option D: No, because they must be manufactured within the same state

LEED regional materials credit is not restricted to materials from the same state. The requirement is based on distance (500-mile radius), not political boundaries. Materials can come from different states, or even different countries, as long as they're within the 500-mile radius.

Memory Technique

Remember '500 and GO' - if materials are within 500 miles for both extraction and manufacturing, you're good to GO for LEED regional credit

Reference Hint

Look up LEED v4 Building Design and Construction reference guide, Materials and Resources section, or Florida Building Code Chapter on Green Building Standards

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.