A contractor is managing a project where steel deliveries are consistently 3 days late. Using CPM analysis, the steel installation activity has a total float of 2 days. What should be the contractor's immediate action?
Correct Answer
A) Expedite steel deliveries or find alternative suppliers immediately
Since steel deliveries are 3 days late but the activity only has 2 days of float, this will delay the project by 1 day. Immediate action to expedite deliveries or secure alternative suppliers is necessary to minimize project impact.
Why This Is the Correct Answer
Option B is correct because when an activity's delay exceeds its available float, it becomes critical and will impact the project completion date. Since steel deliveries are 3 days late but only have 2 days of float, this creates a 1-day delay to the overall project. The contractor must take immediate corrective action to expedite deliveries or secure alternative suppliers to minimize further project delays. Waiting or accepting the delay would compound the problem and potentially lead to additional costs and schedule impacts.
Why the Other Options Are Wrong
Option B: Reschedule other activities to create more float
Option D is wrong because rescheduling other activities cannot create more float for the steel installation activity that is already delayed. Float is determined by the critical path, and moving other activities won't help if steel installation becomes the new critical path constraint.
Option D: Continue with the current schedule since the delay is manageable
Option C is wrong because simply adjusting the completion date is a reactive approach that accepts the delay without attempting to mitigate it. The contractor should first try to recover the schedule through expediting or alternative suppliers before accepting a delayed completion.
Memory Technique
Remember 'Float vs. Fate': When delays exceed float, you control the project's fate by taking immediate action rather than accepting the delay.
Reference Hint
Project Management chapter, specifically sections on Critical Path Method (CPM), float calculations, and schedule recovery techniques
More Business & Finance Questions
A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?
What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?
A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?
When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?
A partnership agreement for a construction company should address all of the following EXCEPT:
A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?
A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?
Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?
A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?
A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?
