A contractor is installing a tile roof in a hurricane zone. What is the minimum wind uplift rating required for the underlayment attachment?
Correct Answer
D) 150 mph
In Florida hurricane zones, roof underlayment must be attached to resist wind uplift of at least 150 mph. This higher standard helps prevent roof failure during severe weather events common in Florida.
Why This Is the Correct Answer
Florida's building code requires roof underlayment in hurricane zones to withstand wind uplift pressures equivalent to 150 mph winds. This stringent requirement reflects Florida's exposure to Category 4 and 5 hurricanes, which can produce sustained winds exceeding 130-157 mph. The 150 mph standard provides adequate safety margin and aligns with the High Velocity Hurricane Zone (HVHZ) requirements found in Miami-Dade and Broward counties. This requirement is critical for preventing catastrophic roof failure during major hurricane events.
Why the Other Options Are Wrong
Option A: 60 mph
60 mph is far too low for hurricane zone requirements and would only be appropriate for areas with minimal wind exposure, not Florida's hurricane-prone regions.
Option B: 90 mph
90 mph represents a moderate wind zone requirement but is insufficient for Florida's hurricane zones where winds regularly exceed this speed during major storms.
Option C: 120 mph
120 mph, while closer to hurricane-force winds, still falls short of Florida's stringent requirements for hurricane zones and would not provide adequate protection during Category 4-5 hurricanes.
Memory Technique
Remember '150 for Florida storms' - the number 150 represents both the minimum mph requirement and roughly the wind speed of a strong Category 4 hurricane that Florida must be prepared for.
Reference Hint
Florida Building Code Chapter 15 - Roof Assemblies and Rooftop Structures, specifically sections on wind uplift resistance and hurricane zone requirements
More Project Mgmt Questions
What is the minimum R-value required for wall insulation in Florida Climate Zone 2?
A subcontractor brings a new chemical product to your jobsite. Under the Globally Harmonized System (GHS), what information must be immediately available to workers?
A construction site has a trench that is 8 feet deep in Type B soil. What is the maximum allowable slope ratio for the trench walls without protective systems?
A detail drawing shows a scale of 3/4" = 1'-0". If a dimension measures 2.25 inches on the drawing, what is the actual dimension?
What is the maximum recommended spacing between drywall screws when attaching to wood studs?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Previous Question
A crane with a 100-ton capacity is lifting a 75-ton load with a 20-foot boom radius. The load chart shows 80-ton capacity at this radius. What is the safety factor?
Next Question
What type of welding process is most commonly used for structural steel connections in commercial construction?