EstatePass
Contract AdminPreconstructionmedium27% of exam part

A contractor is estimating labor costs for installing 2,400 square feet of ceramic tile. If the productivity rate is 25 square feet per hour and the labor rate is $32 per hour including benefits, what is the total labor cost?

Correct Answer

D) $3,072

First calculate total hours: 2,400 sq ft ÷ 25 sq ft/hour = 96 hours. Then multiply by labor rate: 96 hours × $32/hour = $3,072.

Answer Options
A
$4,096
B
$3,584
C
$2,560
D
$3,072

Why This Is the Correct Answer

Option B is correct because it follows the proper two-step labor cost calculation method. First, you determine the total hours needed by dividing the total square footage (2,400) by the productivity rate (25 sq ft/hour), which equals 96 hours. Then you multiply the total hours by the hourly labor rate ($32/hour) to get the total labor cost of $3,072.

Why the Other Options Are Wrong

Option A: $4,096

This answer ($4,096) uses an incorrect hourly rate of approximately $42.67, which is significantly higher than the given $32/hour rate including benefits.

Option C: $2,560

This answer ($3,584) suggests using an inflated hourly rate of approximately $37.33 instead of the given $32/hour, possibly adding unnecessary markups or miscalculating.

Memory Technique

Remember 'DPR' - Divide by Productivity Rate first, then multiply by hourly Rate. Think 'Hours first, dollars second' to avoid mixing up the calculation sequence.

Reference Hint

Look up labor productivity rates and cost estimation methods in the Construction Estimating or Project Management chapters of your contractor reference manual.

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.