A contractor is estimating labor costs for installing 2,000 square feet of ceramic tile. The productivity rate is 25 square feet per hour, and the labor rate is $32 per hour. What is the total labor cost?
Correct Answer
B) $2,560
Total hours needed = 2,000 sq ft ÷ 25 sq ft/hr = 80 hours. Total labor cost = 80 hours × $32/hr = $2,560.
Why This Is the Correct Answer
Option B is correct because it follows the proper two-step labor cost calculation method. First, we determine the total hours needed by dividing the total square footage (2,000) by the productivity rate (25 sq ft/hr), which equals 80 hours. Then we multiply those hours by the hourly labor rate ($32/hr) to get the total labor cost of $2,560.
Why the Other Options Are Wrong
Option A: $1,600
This answer ($1,600) appears to be calculated by dividing the total square footage by the hourly rate (2,000 ÷ $32 = 62.5, then rounded), which is an incorrect method that skips the productivity rate calculation entirely.
Option C: $3,200
This answer ($3,200) incorrectly multiplies the total square footage by the hourly rate (2,000 × $32 ÷ 20 = $3,200), suggesting a miscalculation in the hours needed or using wrong productivity assumptions.
Option D: $4,800
This answer ($4,800) appears to use an incorrect productivity rate calculation, possibly assuming 60 hours instead of 80 hours, or using a different hourly rate in the calculation.
Memory Technique
Remember 'DivMult' - DIVide total work by productivity rate to get hours, then MULTiply hours by hourly rate to get total cost. The units should cancel out properly: sq ft ÷ (sq ft/hr) = hr, then hr × ($/hr) = $.
Reference Hint
Construction estimating section, specifically labor productivity rates and cost calculations chapter in your contractor reference manual
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass