A contractor is estimating concrete work for a 2,400 square foot slab. The concrete cost is $120 per cubic yard, and the slab is 4 inches thick. What is the material cost for concrete only?
Correct Answer
A) $3,555
Calculate volume: 2,400 sq ft × (4 inches ÷ 12) = 800 cubic feet. Convert to cubic yards: 800 ÷ 27 = 29.63 cubic yards. Cost: 29.63 × $120 = $3,555.
Why This Is the Correct Answer
The correct answer follows the proper sequence of converting square footage to cubic feet by multiplying by thickness in feet, then converting cubic feet to cubic yards by dividing by 27, and finally multiplying by the unit cost. The calculation yields 2,400 × (4/12) = 800 cubic feet, then 800 ÷ 27 = 29.63 cubic yards, and finally 29.63 × $120 = $3,555. This systematic approach ensures accurate volume calculation and cost estimation.
Why the Other Options Are Wrong
Option B: $4,267
This answer likely results from incorrectly calculating the volume or using wrong conversion factors, possibly calculating 26.67 cubic yards instead of 29.63 cubic yards.
Option C: $3,200
This answer suggests an error in the conversion process, possibly multiplying by incorrect factors or failing to properly convert inches to feet before calculating volume.
Memory Technique
Remember '27 magic number' - there are 27 cubic feet in 1 cubic yard (3×3×3). Also remember 'Inches to Feet to Yards' - always convert in this order to avoid mistakes.
Reference Hint
Florida Building Code or construction estimating references - Chapter on concrete work and material calculations, unit conversion tables
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?