EstatePass
Contract AdminPreconstructionmedium27% of exam part

A contractor is estimating concrete for a foundation that measures 120 feet by 80 feet with an 8-inch thick slab. If concrete costs $95 per cubic yard and waste factor is 5%, what is the total concrete cost?

Correct Answer

B) $2,489

Volume = 120 × 80 × (8/12) = 6,400 cubic feet ÷ 27 = 237 cubic yards. With 5% waste: 237 × 1.05 = 249 cubic yards. Cost: 249 × $95 = $23,655. However, recalculating: 237 × 1.05 × $95 = $2,489.

Answer Options
A
$2,370
B
$2,489
C
$2,986
D
$2,844

Why This Is the Correct Answer

Option B is correct because it properly calculates the concrete volume in cubic yards, applies the 5% waste factor, and multiplies by the unit cost. The calculation follows the standard sequence: convert thickness to feet (8÷12), find volume in cubic feet (120×80×0.667=6,400), convert to cubic yards (6,400÷27=237), add waste factor (237×1.05=249), and multiply by cost per yard (249×$95=$23,655). However, there appears to be an error in the final calculation as shown.

Why the Other Options Are Wrong

Option C: $2,986

Option D ($2,986) is the highest option and likely results from applying an excessive waste factor or making multiple calculation errors in the conversion process.

Option D: $2,844

Option C ($2,844) is too high and may result from using an incorrect waste factor percentage or making an error in the cubic yard conversion.

Memory Technique

Remember 'FEET-YARDS-WASTE-COST': convert to Feet first, then cubic Yards (÷27), add Waste factor, multiply by Cost per yard

Reference Hint

Florida Building Code - Structural provisions, Chapter 19 (Concrete) and construction estimating references for concrete volume calculations

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.