EstatePass
Business & FinanceAccountingmedium32% of exam part

A contractor has the following for a project: Contract amount $400,000, Costs incurred $240,000, Estimated costs to complete $120,000. What percentage of the project is complete using the cost-to-cost method?

Correct Answer

B) 67%

Percentage complete = Costs incurred ÷ Total estimated costs. Total estimated costs = $240,000 + $120,000 = $360,000. Percentage complete = $240,000 ÷ $360,000 = 66.7% or 67%.

Answer Options
A
60%
B
67%
C
75%
D
80%

Why This Is the Correct Answer

The cost-to-cost method calculates project completion percentage by dividing costs incurred by total estimated project costs. Total estimated costs equal costs incurred ($240,000) plus estimated costs to complete ($120,000), which equals $360,000. Dividing costs incurred ($240,000) by total estimated costs ($360,000) gives 66.7%, which rounds to 67%.

Why the Other Options Are Wrong

Option A: 60%

60% would result from incorrectly dividing costs incurred ($240,000) by the contract amount ($400,000), which is not the cost-to-cost method formula.

Option C: 75%

75% would result from an incorrect calculation, possibly confusing the denominator or using wrong cost figures in the cost-to-cost formula.

Option D: 80%

80% appears to be a random percentage that doesn't correspond to any logical calculation using the given project cost data.

Memory Technique

Remember 'CTC' - Cost-To-Cost method uses Costs incurred divided by Total Costs (incurred plus remaining costs to complete).

Reference Hint

Look up 'Percentage of Completion Method' or 'Cost-to-Cost Method' in accounting or project management sections of your reference materials.

More Business & Finance Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing