A contractor faces a cash flow shortage and needs to decide between two options: factor receivables at 3% discount or take a bank loan at 8% annual interest for 60 days. Which option has the lower effective cost?
Correct Answer
C) Bank loan (8% annual interest for 60 days)
Bank loan cost for 60 days = 8% × (60/365) = 1.32%. Factoring costs 3% immediately. The bank loan has a lower effective cost.
Why This Is the Correct Answer
Bank loan cost for 60 days = 8% × (60/365) = 1.32%. Factoring costs 3% immediately. The bank loan has a lower effective cost.
More NASCLA Questions
Which AIA document contains the general conditions that govern the rights and responsibilities of all parties in a construction contract?
A construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?
What is the primary purpose of job cost accounting in construction?
A construction company has current assets of $350,000 and current liabilities of $280,000. What is the company's working capital?
In CSI MasterFormat, which division covers earthwork and site preparation?
In a mechanical drawing, what does 'CFM' typically measure?
In CSI MasterFormat Division 08, which of the following would typically be included?
On a mechanical plan, what does the symbol 'RTU' typically indicate?
What is the minimum preheat temperature for welding ASTM A992 steel when the ambient temperature is 15°F?
A general contractor's balance sheet shows total assets of $850,000, current liabilities of $320,000, and long-term debt of $180,000. What is the company's equity?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
When performing a quantity takeoff for paint, which approach accounts for the most accurate coverage calculation?
Next Question
A contractor is deciding between purchasing a $45,000 excavator or renting one for $350 per day. The project will require the excavator for 85 days, and the contractor estimates using it on future projects 120 days per year. What is the most cost-effective decision for the first year?
