A contractor discovers that a key material supplier cannot deliver concrete on the scheduled date, potentially delaying the critical path by 3 days. What is the most appropriate immediate action?
Correct Answer
C) Find an alternative supplier or expedite delivery from another source
When facing a critical path delay due to material availability, the first action should be to expedite delivery through alternative suppliers or methods. This maintains the original schedule and avoids costly delays.
Why This Is the Correct Answer
Option C is correct because when facing a critical path delay, the immediate priority is to maintain the original schedule through alternative sourcing. Finding another supplier or expediting delivery addresses the root cause of the problem without accepting delays or making costly changes to the project. This approach preserves the project timeline and budget while solving the immediate material availability issue. It's the most direct and cost-effective solution that maintains project momentum.
Why the Other Options Are Wrong
Option A: Accept the delay and adjust the overall schedule
Option A is wrong because accepting delays should be a last resort, not the immediate action. Simply adjusting the schedule without first attempting to resolve the material issue ignores potential solutions and unnecessarily extends the project timeline, which can lead to increased costs, contract penalties, and cascading delays to other project activities.
Option B: Crash other activities to make up the time
Option B is wrong because crashing other activities is expensive and should only be considered after exhausting material sourcing options. Crashing involves adding resources or working overtime, which increases costs significantly. It's premature to crash activities when the original problem (material availability) might be solvable through alternative suppliers.
Option D: Switch to a different construction method
Option D is wrong because switching construction methods is a major change that requires design modifications, permit revisions, and potentially different materials and labor skills. This creates more delays and complications than the original 3-day material delay and should only be considered for long-term material shortages, not immediate delivery issues.
Memory Technique
Think 'SOURCE first' - when materials are the problem, find alternative SOURCES before accepting delays or making expensive changes
Reference Hint
Project Management chapter covering Critical Path Method (CPM) and schedule compression techniques
More Business & Finance Questions
A contractor's license expires on March 31st. If they submit a renewal application on April 15th, what additional requirement must be met under Florida regulations?
A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?
In Florida, what is the minimum workers' compensation insurance coverage required for construction companies with employees?
What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?
A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?
People Also Study
Previous Question
A contractor hires 3 workers as independent contractors, paying each $2,400 per month. If reclassified as employees, what would be the total monthly unemployment tax liability assuming a 2.7% state rate?
Next Question
When conducting performance evaluations, which approach is considered most effective for employee development?