EstatePass
Business & FinanceOperationsmedium10% of exam part

A contractor discovers that a key material supplier cannot deliver concrete on the scheduled date, potentially delaying the critical path by 3 days. What is the most appropriate immediate action?

Correct Answer

C) Find an alternative supplier or expedite delivery from another source

When facing a critical path delay due to material availability, the first action should be to expedite delivery through alternative suppliers or methods. This maintains the original schedule and avoids costly delays.

Answer Options
A
Accept the delay and adjust the overall schedule
B
Crash other activities to make up the time
C
Find an alternative supplier or expedite delivery from another source
D
Switch to a different construction method

Why This Is the Correct Answer

Option C is correct because when facing a critical path delay, the immediate priority is to maintain the original schedule through alternative sourcing. Finding another supplier or expediting delivery addresses the root cause of the problem without accepting delays or making costly changes to the project. This approach preserves the project timeline and budget while solving the immediate material availability issue. It's the most direct and cost-effective solution that maintains project momentum.

Why the Other Options Are Wrong

Option A: Accept the delay and adjust the overall schedule

Option A is wrong because accepting delays should be a last resort, not the immediate action. Simply adjusting the schedule without first attempting to resolve the material issue ignores potential solutions and unnecessarily extends the project timeline, which can lead to increased costs, contract penalties, and cascading delays to other project activities.

Option B: Crash other activities to make up the time

Option B is wrong because crashing other activities is expensive and should only be considered after exhausting material sourcing options. Crashing involves adding resources or working overtime, which increases costs significantly. It's premature to crash activities when the original problem (material availability) might be solvable through alternative suppliers.

Option D: Switch to a different construction method

Option D is wrong because switching construction methods is a major change that requires design modifications, permit revisions, and potentially different materials and labor skills. This creates more delays and complications than the original 3-day material delay and should only be considered for long-term material shortages, not immediate delivery issues.

Memory Technique

Think 'SOURCE first' - when materials are the problem, find alternative SOURCES before accepting delays or making expensive changes

Reference Hint

Project Management chapter covering Critical Path Method (CPM) and schedule compression techniques

More Business & Finance Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing