A contractor discovers differing site conditions that will require additional excavation costing $45,000 and extending the schedule by 10 days. The contract includes a differing site conditions clause. What is the contractor's first step?
Correct Answer
D) Provide written notice to the owner before disturbing the conditions
When differing site conditions are encountered, the contractor must typically provide prompt written notice to the owner before disturbing the conditions, allowing for inspection and documentation of the conditions.
Why This Is the Correct Answer
When differing site conditions are encountered, the contractor must provide prompt written notice to the owner (and typically the architect) before disturbing the conditions. This preserves the owner's right to inspect and document the actual conditions, which is essential for evaluating the claim. Disturbing conditions before notice can destroy the evidence and waive the contractor's right to compensation.
Why the Other Options Are Wrong
Option A: Immediately proceed with the additional work
Immediately proceeding with the additional work is the worst option. Proceeding without notice destroys the conditions the owner needs to inspect and can waive the contractor's contractual right to additional compensation.
Option B: Submit a change order request
Submitting a change order request is premature as the first step. The change order process begins after the owner has been notified and has had the opportunity to inspect. Notice must come first.
Option C: File a claim for extra compensation
Filing a claim for extra compensation is also premature as the first step. Claims come after proper notice and the owner's failure to resolve the issue through a change order or directive. The claim process is the last resort, not the first step.
Memory Technique
DSC = Discover → Stop → Call (notify in writing). Like a crime scene — don't touch anything until you've notified the authorities (owner). Preserve the evidence first.
More NASCLA Questions
How long should daily reports and project correspondence typically be retained after project completion?
Which AIA document contains the general conditions that govern the rights and responsibilities of all parties in a construction contract?
A construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?
What is the primary purpose of job cost accounting in construction?
A construction company has current assets of $350,000 and current liabilities of $280,000. What is the company's working capital?
In CSI MasterFormat, which division covers earthwork and site preparation?
On an electrical plan, a rectangle with three parallel lines inside typically represents:
In a mechanical drawing, what does 'CFM' typically measure?
In CSI MasterFormat Division 08, which of the following would typically be included?
On a mechanical plan, what does the symbol 'RTU' typically indicate?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Project Management
60 questions · 70% to pass
