A contractor applies for a building permit on Monday. The local building department has 30 calendar days to review the application. If no response is received by the deadline, what happens to the permit application?
Correct Answer
B) The application is automatically approved
Under Florida law, if a building department does not respond to a permit application within the specified timeframe (typically 30 days), the application is deemed automatically approved. This prevents unnecessary delays in the permitting process.
Why This Is the Correct Answer
Florida Statutes Section 125.022 and 166.033 establish the 'deemed approved' rule for building permits. This statutory provision ensures that local governments cannot indefinitely delay construction projects by failing to act on permit applications. The automatic approval mechanism protects contractors and property owners from bureaucratic delays while still allowing reasonable time for proper review. This rule applies when the building department fails to approve, approve with conditions, or deny the application within the specified timeframe.
Why the Other Options Are Wrong
Option A: The application is automatically denied
Automatic denial would be counterproductive and unfair to applicants, as it would penalize them for the building department's failure to act timely. Florida law specifically protects against this outcome.
Option C: The review period is extended by 15 days
There is no provision in Florida law for automatic extensions of the review period. The 30-day timeframe is firm, and failure to act results in deemed approval, not extended review time.
Option D: The contractor must resubmit the application
Requiring resubmission would create an endless loop that could allow building departments to indefinitely delay projects by simply not responding. Florida law prevents this by making approval automatic.
Memory Technique
Think 'No News is Good News' - when the building department gives you no response by the deadline, that's good news because it means automatic approval.
Reference Hint
Florida Statutes Chapter 125.022 (counties) and 166.033 (municipalities) - Local Government Comprehensive Planning sections
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
What is the recommended contingency percentage for renovation work compared to new construction?
Next Question
A complex project has multiple critical paths with durations of 180, 185, and 190 days respectively. The project experiences a 3-day delay on the path with 185-day duration. What is the new project duration?