A construction project will impact 0.75 acres of wetlands. The mitigation requirement is 2:1 replacement ratio. How many acres of wetland mitigation must be provided?
Correct Answer
C) 1.5 acres
With a 2:1 mitigation ratio, the required mitigation is: 0.75 acres impacted × 2 = 1.5 acres of wetland mitigation. This ensures no net loss of wetland functions and values.
Why This Is the Correct Answer
Option C is correct because wetland mitigation follows a simple multiplication formula. When the impact is 0.75 acres and the required mitigation ratio is 2:1, you multiply the impacted area by the ratio factor. This calculation yields 0.75 × 2 = 1.5 acres of required mitigation. The 2:1 ratio ensures that for every acre of wetland lost, two acres are restored or created to maintain ecological balance.
Why the Other Options Are Wrong
Option A: 1.0 acres
Option A (1.0 acres) represents an incorrect 1.33:1 ratio, which would be insufficient mitigation under typical regulatory requirements and would not provide adequate compensation for wetland functions lost.
Option B: 1.25 acres
Option B (1.25 acres) represents an incorrect 1.67:1 ratio, which falls short of the required 2:1 mitigation standard and would not meet regulatory compliance requirements.
Option D: 2.0 acres
Option D (2.0 acres) would represent a 2.67:1 ratio, which exceeds the required mitigation and would result in unnecessary additional costs and land use for the project.
Memory Technique
Remember 'IMPACT × RATIO = MITIGATION' - think of it as 'paying double' for environmental damage. The ratio tells you how many times larger your mitigation must be than your impact.
Reference Hint
Florida Building Code Chapter 1, Environmental Regulations section, or DEP Chapter 62-330 F.A.C. regarding wetland mitigation requirements
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
What is the primary advantage of using the assemblies cost estimating method over the square foot method?
Next Question
A time and materials contract has a labor rate of $85 per hour with a 15% markup on materials. If a project requires 120 hours of labor and $8,500 in materials, what is the total contract amount?