EstatePass
Contract AdminPermitshard20% of exam part

A construction project requires environmental impact assessment due to potential endangered species habitat. The assessment costs $28,000 and takes 120 days. If project delays cost $1,200 per day, what is the total environmental compliance cost?

Correct Answer

A) $172,000

Total cost includes assessment fee ($28,000) plus delay costs (120 days × $1,200 = $144,000) for a total of $172,000.

Answer Options
A
$172,000
B
$144,000
C
$156,000
D
$28,000

Why This Is the Correct Answer

The total environmental compliance cost must include both direct costs and indirect costs. The direct cost is the $28,000 assessment fee, while the indirect cost is the project delay expense of 120 days × $1,200 per day = $144,000. Adding these together gives the complete environmental compliance cost of $172,000, which represents the true total cost impact to the project.

Why the Other Options Are Wrong

Option C: $156,000

This amount doesn't correspond to any logical combination of the given costs and appears to be a distractor answer that might result from calculation errors.

Option D: $28,000

This represents only the delay costs (120 days × $1,200 = $144,000) but fails to include the actual assessment fee of $28,000, making it an incomplete calculation.

Memory Technique

Remember 'TOTAL = DIRECT + DELAY' - environmental costs always include both the study/assessment fees AND the time-related project delay costs

Reference Hint

Florida Building Code Chapter 1, Administrative provisions regarding environmental compliance requirements and project cost calculations

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.