EstatePass
Contract AdminProcedureshard13% of exam part

A construction project has a critical path of 120 days. Activity Y has 8 days of total float. If Activity Y is delayed by 12 days due to material delivery issues, what happens to the project completion date?

Correct Answer

D) Project is delayed by 4 days

Activity Y can be delayed up to 8 days (its total float) without affecting the project. Since it's delayed 12 days, the excess delay of 4 days (12-8=4) will delay the entire project by 4 days.

Answer Options
A
Project is delayed by 8 days
B
Project is delayed by 12 days
C
No change - project completes on time
D
Project is delayed by 4 days

Why This Is the Correct Answer

Activity Y has 8 days of total float, meaning it can be delayed up to 8 days without impacting the project's critical path. When delayed by 12 days, only the first 8 days are absorbed by the float. The remaining 4 days (12 - 8 = 4) exceed the available float and directly delay the project completion date by 4 days.

Why the Other Options Are Wrong

Option B: Project is delayed by 12 days

This is incorrect because Activity Y's delay of 12 days exceeds its total float of 8 days. While the first 8 days of delay are absorbed by the float, the remaining 4 days will impact the project completion date.

Option C: No change - project completes on time

This assumes the entire float amount becomes the project delay, which is incorrect. The project delay equals only the amount by which the activity delay exceeds its available float (12 - 8 = 4 days), not the full float value.

Memory Technique

Think 'Float First' - float absorbs delays first like a shock absorber. Only delays beyond the float capacity affect the project: Delay Impact = Activity Delay - Available Float (if positive).

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.