A construction project has a critical path of 120 days. Activity Y has 8 days of total float. If Activity Y is delayed by 12 days due to material delivery issues, what happens to the project completion date?
Correct Answer
D) Project is delayed by 4 days
Activity Y can be delayed up to 8 days (its total float) without affecting the project. Since it's delayed 12 days, the excess delay of 4 days (12-8=4) will delay the entire project by 4 days.
Why This Is the Correct Answer
Activity Y has 8 days of total float, meaning it can be delayed up to 8 days without impacting the project's critical path. When delayed by 12 days, only the first 8 days are absorbed by the float. The remaining 4 days (12 - 8 = 4) exceed the available float and directly delay the project completion date by 4 days.
Why the Other Options Are Wrong
Option B: Project is delayed by 12 days
This is incorrect because Activity Y's delay of 12 days exceeds its total float of 8 days. While the first 8 days of delay are absorbed by the float, the remaining 4 days will impact the project completion date.
Option C: No change - project completes on time
This assumes the entire float amount becomes the project delay, which is incorrect. The project delay equals only the amount by which the activity delay exceeds its available float (12 - 8 = 4 days), not the full float value.
Memory Technique
Think 'Float First' - float absorbs delays first like a shock absorber. Only delays beyond the float capacity affect the project: Delay Impact = Activity Delay - Available Float (if positive).
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
