A construction crew is working near an overhead power line. If the line voltage is unknown, what is the minimum safe clearance distance required?
Correct Answer
B) 10 feet
When voltage is unknown, OSHA requires a minimum 10-foot clearance from overhead power lines for construction equipment and workers.
Why This Is the Correct Answer
OSHA 29 CFR 1926.416(a)(1) specifies that when voltage is unknown, workers and equipment must maintain a minimum clearance of 10 feet from overhead power lines. This 10-foot default applies specifically because the voltage is unknown — without knowing the voltage, you cannot use the voltage-specific clearance tables, so OSHA defaults to the general 10-foot rule. This clearance applies to all tools, equipment, and workers.
Why the Other Options Are Wrong
Option A: 20 feet
20 feet is the minimum clearance required for lines operating at voltages above 350 kV up to 500 kV, or in some references for cranes near high-voltage lines. It is not the general unknown-voltage default for construction crews.
Option C: 6 feet
6 feet is not an OSHA standard clearance distance for power lines. It may be confused with other clearance requirements (such as minimum working space around electrical panels) but does not apply to overhead power line proximity.
Option D: 15 feet
15 feet applies to specific voltage ranges (over 50 kV up to 200 kV in some regulations) or to crane operations near certain power line voltages. It is not the standard unknown-voltage default clearance for general construction work.
Memory Technique
Power line unknown = 10 feet minimum. Think of 10 as the baseline safety number for electrical clearances. 'When in doubt, stay 10 out.' Cranes and larger equipment have stricter requirements, but for workers and hand tools, 10 feet is the unknown-voltage default.
More NASCLA Questions
Which AIA document contains the general conditions that govern the rights and responsibilities of all parties in a construction contract?
A construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?
What is the primary purpose of job cost accounting in construction?
A construction company has current assets of $350,000 and current liabilities of $280,000. What is the company's working capital?
In CSI MasterFormat, which division covers earthwork and site preparation?
In a mechanical drawing, what does 'CFM' typically measure?
In CSI MasterFormat Division 08, which of the following would typically be included?
On a mechanical plan, what does the symbol 'RTU' typically indicate?
What is the minimum preheat temperature for welding ASTM A992 steel when the ambient temperature is 15°F?
A general contractor's balance sheet shows total assets of $850,000, current liabilities of $320,000, and long-term debt of $180,000. What is the company's equity?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
A cut and fill operation requires moving 2,400 cubic yards of soil. The soil has a swell factor of 25% when excavated and a shrinkage factor of 8% when compacted. How many cubic yards must be excavated to achieve 2,400 cubic yards of compacted fill?
Next Question
A roofing crew can install 35 squares per day. The project requires 280 squares. Crew cost is $2,400/day, and material cost is $165/square. What is the total cost?
