A construction company has a project that started with a contract value of $500,000. To date, they have incurred costs of $300,000 and estimate $150,000 more to complete. What is the estimated gross profit on this project?
Correct Answer
A) $50,000
Total estimated costs = $300,000 (incurred) + $150,000 (to complete) = $450,000. Estimated gross profit = $500,000 (contract value) - $450,000 (total estimated costs) = $50,000.
Why This Is the Correct Answer
To calculate estimated gross profit, you must first determine the total estimated project costs by adding costs already incurred to the estimated costs to complete. Then subtract this total from the contract value. The calculation is: Total estimated costs = $300,000 + $150,000 = $450,000, then Gross profit = $500,000 - $450,000 = $50,000.
Why the Other Options Are Wrong
Option B: $150,000
This incorrectly uses only the estimated costs to complete ($150,000) as the gross profit, ignoring the costs already incurred. This would overstate the profit significantly.
Option C: $200,000
This appears to subtract only the incurred costs ($300,000) from the contract value ($500,000), failing to account for the remaining $150,000 needed to complete the project.
Option D: $300,000
This simply states the incurred costs to date ($300,000) as the profit, which makes no sense as it ignores both the contract value and remaining costs.
Memory Technique
Remember 'CTC' - Contract minus Total Costs equals profit. Total costs always include both money spent AND money still needed.
Reference Hint
Look up project accounting and cost control sections in construction management references, particularly chapters on job costing and profit calculation.
More Business & Finance Questions
A contractor's license expires on March 31st. If they submit a renewal application on April 15th, what additional requirement must be met under Florida regulations?
A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?
In Florida, what is the minimum workers' compensation insurance coverage required for construction companies with employees?
What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?
A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?
People Also Study
Previous Question
A contractor has annual overhead costs of $240,000 and expects to generate $1,200,000 in direct costs for the year. What is the overhead percentage that should be applied to bids?
Next Question
During bid preparation, a general contractor discovers that a key subcontractor has submitted a bid 30% lower than all other comparable bids. What is the most appropriate action?