EstatePass
Contract AdminProceduresmedium13% of exam part

A concrete pour is scheduled for tomorrow, but the quality control inspector identifies that the rebar spacing does not meet specifications. What action should be taken?

Correct Answer

B) Stop work, correct the rebar spacing, and reschedule the pour

Work must be stopped and the rebar spacing corrected to meet specifications before proceeding with the concrete pour. Quality control requires adherence to specifications for structural integrity and code compliance.

Answer Options
A
Pour the concrete but document the deviation for future reference
B
Stop work, correct the rebar spacing, and reschedule the pour
C
Proceed with the pour since concrete will hold the rebar in place
D
Reduce the concrete strength to compensate for rebar spacing

Why This Is the Correct Answer

Option B is correct because structural integrity and code compliance require strict adherence to engineering specifications. Rebar spacing is critical for proper load distribution and concrete reinforcement - deviations can lead to structural failure. Florida Building Code and ACI standards mandate that work must stop when specifications are not met, corrections must be made, and proper inspection must occur before proceeding. This protects public safety and ensures the contractor meets legal and professional obligations.

Why the Other Options Are Wrong

Option A: Pour the concrete but document the deviation for future reference

This option ignores the fundamental purpose of rebar reinforcement and violates building codes. Concrete alone cannot provide adequate tensile strength, and improper rebar spacing creates weak points that can lead to structural failure under load.

Option D: Reduce the concrete strength to compensate for rebar spacing

Simply documenting a known code violation while proceeding with defective work is negligent and violates professional standards. This creates liability for the contractor and compromises structural integrity, making it unacceptable regardless of documentation.

Memory Technique

Use 'SCP' - Stop, Correct, Proceed. Never skip steps when structural specifications are not met.

Reference Hint

Florida Building Code Chapter 19 (Concrete) and ACI 318 Building Code Requirements for Structural Concrete - sections on reinforcement placement and inspection requirements

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.