EstatePass
Contract AdminProceduresmedium13% of exam part

A concrete pour is scheduled for tomorrow, but the quality control inspector identifies that the rebar spacing does not meet specifications. What action should be taken?

Correct Answer

B) Stop work, correct the rebar spacing, and reschedule the pour

Work must be stopped and the rebar spacing corrected to meet specifications before proceeding with the concrete pour. Quality control requires adherence to specifications for structural integrity and code compliance.

Answer Options
A
Proceed with the pour since concrete will hold the rebar in place
B
Stop work, correct the rebar spacing, and reschedule the pour
C
Pour the concrete but document the deviation for future reference
D
Reduce the concrete strength to compensate for rebar spacing

Why This Is the Correct Answer

Option B is correct because structural integrity and code compliance require strict adherence to engineering specifications. Rebar spacing is critical for proper load distribution and concrete reinforcement - deviations can lead to structural failure. Florida Building Code and ACI standards mandate that work must stop when specifications are not met, corrections must be made, and proper inspection must occur before proceeding. This protects public safety and ensures the contractor meets legal and professional obligations.

Why the Other Options Are Wrong

Option A: Proceed with the pour since concrete will hold the rebar in place

This option ignores the fundamental purpose of rebar reinforcement and violates building codes. Concrete alone cannot provide adequate tensile strength, and improper rebar spacing creates weak points that can lead to structural failure under load.

Option C: Pour the concrete but document the deviation for future reference

Simply documenting a known code violation while proceeding with defective work is negligent and violates professional standards. This creates liability for the contractor and compromises structural integrity, making it unacceptable regardless of documentation.

Option D: Reduce the concrete strength to compensate for rebar spacing

Concrete strength and rebar spacing serve different structural functions and cannot be arbitrarily substituted. This approach violates engineering principles and building codes, and could result in catastrophic structural failure.

Memory Technique

Use 'SCP' - Stop, Correct, Proceed. Never skip steps when structural specifications are not met.

Reference Hint

Florida Building Code Chapter 19 (Concrete) and ACI 318 Building Code Requirements for Structural Concrete - sections on reinforcement placement and inspection requirements

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing