A concrete pour is scheduled for 8 hours with a crew of 6 workers at $35/hour each. Due to weather delays, the pour takes 12 hours and requires 2 additional workers for the last 4 hours. What is the total labor cost variance?

Correct Answer

B) $840 over budget

Budgeted: 6 workers × 8 hours × $35 = $1,680. Actual: (6 workers × 12 hours × $35) + (2 workers × 4 hours × $35) = $2,520 + $280 = $2,800. Variance = $2,800 - $1,680 = $1,120 over budget.

Answer Options
A
$560 over budget
B
$840 over budget
C
$420 over budget
D
$1,120 over budget

Why This Is the Correct Answer

Budgeted: 6 workers × 8 hours × $35 = $1,680. Actual: (6 workers × 12 hours × $35) + (2 workers × 4 hours × $35) = $2,520 + $280 = $2,800. Variance = $2,800 - $1,680 = $1,120 over budget.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.