EstatePass
Contract AdminProcedureshard13% of exam part

A complex project has multiple critical paths with durations of 180, 185, and 190 days respectively. The project experiences a 3-day delay on the path with 185-day duration. What is the new project duration?

Correct Answer

C) 190 days

The project duration is determined by the longest path. The 190-day path remains the critical path, so the project duration stays at 190 days since the delayed path (188 days) is still shorter.

Answer Options
A
185 days
B
188 days
C
190 days
D
193 days

Why This Is the Correct Answer

CORRECT_ANSWER - In project management, the overall project duration is always determined by the longest critical path. Even though the 185-day path experienced a 3-day delay making it 188 days, the 190-day path remains unchanged and is still the longest. Since 190 days > 188 days > 180 days, the project duration remains 190 days.

Why the Other Options Are Wrong

Option A: 185 days

185 days represents the original duration of the delayed path, but this ignores both the delay that occurred and the fact that there's a longer 190-day path that determines the overall project duration.

Option B: 188 days

188 days is the new duration of the delayed path (185 + 3), but this path is still not the longest path in the project, so it doesn't determine the overall project duration.

Option D: 193 days

193 days incorrectly adds the 3-day delay to the longest path (190 + 3), but the delay occurred on the 185-day path, not the 190-day path.

Memory Technique

Remember 'LPR' - Longest Path Rules. The project is only as fast as its slowest (longest) path, just like a chain is only as strong as its weakest link.

Reference Hint

Look up 'Critical Path Method (CPM)' and 'Project Scheduling' in construction management or project management chapters

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing