A commercial development project requires multiple permits with the following fees: Building permit $45,000, Site development permit $12,500, Environmental permit $8,200, and Electrical permit $3,800. If the jurisdiction offers a 5% discount for paying all permits simultaneously, what is the total cost?
Correct Answer
A) $66,125
Total permit fees are $45,000 + $12,500 + $8,200 + $3,800 = $69,500. With a 5% discount: $69,500 × 0.95 = $66,125.
Why This Is the Correct Answer
The correct answer systematically adds all four permit fees to get the base total, then applies the 5% discount for simultaneous payment. First, we calculate $45,000 + $12,500 + $8,200 + $3,800 = $69,500. Then we apply the 5% discount by multiplying by 0.95 (which represents paying 95% of the original cost). This gives us $69,500 × 0.95 = $66,125.
Why the Other Options Are Wrong
Option B: $69,500
This represents the total permit fees before applying the 5% discount ($69,500), but fails to account for the cost savings from paying all permits simultaneously.
Option C: $72,975
This amount ($72,975) appears to incorrectly add 5% to the base total instead of subtracting 5%, treating the discount as an additional fee rather than a reduction.
Option D: $69,975
This amount ($69,975) suggests an incorrect calculation that doesn't properly apply the 5% discount to the total permit fees.
Memory Technique
Remember 'BSEE' for the four common commercial permits: Building, Site development, Environmental, Electrical. For discounts, think '95 cents on the dollar' for a 5% discount.
Reference Hint
Florida Building Code Chapter 1 - Administration and Enforcement, specifically sections on permit fees and payment procedures
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass