A building permit application is submitted on Monday morning. The building department has 30 calendar days to review. If no holidays occur during this period, what is the latest date the department must respond?
Correct Answer
A) 30 days from Monday
Most Florida jurisdictions require building departments to respond to permit applications within 30 calendar days from the date of submission, which would be 30 days from Monday when it was submitted.
Why This Is the Correct Answer
Florida building departments are required by state law to review and respond to building permit applications within 30 calendar days from the date of submission. Since the application was submitted on Monday morning, the department has exactly 30 calendar days from that Monday to provide their response. Calendar days include weekends and non-holidays, making this a firm deadline that starts counting immediately from the submission date.
Why the Other Options Are Wrong
Option B: The following Wednesday
Wednesday would only be 2 days after Monday, which is far too short for the legally required review period. Building departments need adequate time to thoroughly review plans, check code compliance, and coordinate with various departments. A 2-day turnaround would be impossible for proper permit review and would not meet Florida's statutory requirements.
Option C: 30 business days from Monday
The law specifically requires response within 30 calendar days, not business days. Business days would exclude weekends and holidays, potentially extending the review period to 6-7 weeks depending on the calendar. This would create uncertainty and delay construction projects unnecessarily, which is why Florida law uses the more definitive calendar day standard.
Option D: 30 calendar days from Tuesday
The 30-day countdown begins on the actual date of submission, which is Monday, not the following day. Starting the count on Tuesday would effectively give the department 31 days to respond, which exceeds the legal requirement. The submission date itself is day one of the review period, ensuring departments meet their statutory obligations promptly.
Memory Technique
Remember '30 Calendar Countdown' - the clock starts ticking on submission day, counting every single day including weekends until day 30.
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
