A building permit application is rejected due to incomplete drawings. The application fee was $850. What portion of the fee is typically refundable?
Correct Answer
B) No refund is provided
Most jurisdictions do not provide refunds for permit application fees, even when applications are rejected for incomplete information. The fee covers the administrative cost of processing and reviewing the application.
Why This Is the Correct Answer
Building permit application fees are typically non-refundable, even when applications are rejected for incomplete drawings or other deficiencies. The fee covers administrative costs including initial review, processing time, and staff resources expended during the application evaluation process. Most jurisdictions maintain this policy because they have already invested time and resources in reviewing the submission, regardless of whether the application ultimately meets all requirements for approval.
Why the Other Options Are Wrong
Option A: 50% of the fee
A 50% refund is not standard practice for rejected permit applications. Jurisdictions typically retain the full fee to cover administrative costs already incurred during the review process, even when applications are incomplete.
Option C: 100% of the fee
A 100% refund would mean the jurisdiction receives no compensation for the time and resources spent reviewing the application. This contradicts standard municipal practices where fees cover administrative processing costs regardless of approval outcome.
Option D: 75% of the fee
A 75% refund is not a standard policy for rejected permit applications. Most jurisdictions do not offer partial refunds since the administrative costs of processing and initial review have already been incurred.
Memory Technique
Remember 'No Refund for Review' - once the jurisdiction starts reviewing your application, they keep the fee regardless of the outcome because they've already spent time and resources on it.
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?