A building permit application fee is calculated as $2.50 per $1,000 of construction value, with a minimum fee of $150. What is the permit fee for a $45,000 renovation project?
Correct Answer
D) $150.00
The calculated fee would be ($45,000 ÷ $1,000) × $2.50 = $112.50. However, since this is below the minimum fee of $150, the permit fee would be $150.
Why This Is the Correct Answer
The correct answer is B) $150.00 because permit fee calculations must always consider both the calculated amount and any minimum fee requirements. First, we calculate the base fee: ($45,000 ÷ $1,000) × $2.50 = $112.50. However, since this calculated amount ($112.50) is less than the minimum required fee of $150, the permit fee defaults to the minimum amount of $150.
Why the Other Options Are Wrong
Option A: $112.50
Option D ($225.00) is significantly higher than both the calculated fee and minimum fee, suggesting an error in applying the rate formula.
Option B: $225.00
Option C ($187.50) appears to be an incorrect calculation that doesn't follow the given formula of $2.50 per $1,000 of construction value.
Option C: $187.50
Option A ($112.50) represents only the calculated fee based on construction value but fails to apply the minimum fee requirement, which is a critical component of permit fee structures.
Memory Technique
Remember 'MIN-MAX': Calculate the fee, then apply the MINimum - take the MAXimum of the two values.
Reference Hint
Florida Building Code Chapter 1 - Scope and Administration, Section on Permits and Fees
More Business & Finance Questions
A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?
What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?
A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?
When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?
A partnership agreement for a construction company should address all of the following EXCEPT:
A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?
A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?
Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?
A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?
A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?
