EstatePass
Business & FinanceAdminhard26% of exam part

A bid submission deadline is 2:00 PM on Friday. Your bid is completed at 1:45 PM but you notice a potential $15,000 error in the electrical subcontractor's quote. What should you do?

Correct Answer

D) Quickly estimate a reasonable adjustment and submit the corrected bid

With only 15 minutes remaining, the best option is to make a reasonable adjustment based on experience and submit the bid. This allows participation while protecting against a significant error that could impact project profitability.

Answer Options
A
Submit the bid as-is and address the error if awarded the contract
B
Do not submit the bid due to the uncertainty
C
Submit the bid with a contingency note about the potential error
D
Quickly estimate a reasonable adjustment and submit the corrected bid

Why This Is the Correct Answer

Option D is correct because it balances business opportunity with risk management. With 15 minutes remaining, there's insufficient time to verify the error with the subcontractor, but a $15,000 mistake could severely impact project profitability. Making a reasonable adjustment based on professional experience and market knowledge allows the contractor to submit a competitive bid while protecting against potential losses. This demonstrates sound business judgment under time pressure.

Why the Other Options Are Wrong

Option A: Submit the bid as-is and address the error if awarded the contract

Submitting a bid with a known potential $15,000 error is extremely risky and poor business practice. If the error results in an underpriced bid and you're awarded the contract, you'll be legally bound to perform at that price, potentially causing significant financial loss. Professional contractors have a responsibility to submit accurate bids based on their best knowledge.

Option B: Do not submit the bid due to the uncertainty

Not submitting the bid means losing a business opportunity entirely. While there's uncertainty about the error, completely withdrawing from the bidding process is overly conservative and could result in lost revenue. The potential error can be reasonably estimated and adjusted for, making non-participation an unnecessarily extreme response.

Option C: Submit the bid with a contingency note about the potential error

Submitting a bid with contingency notes about potential errors is unprofessional and typically unacceptable to owners. Bids should be firm, complete proposals. Conditional bids or those with disclaimers about pricing errors are usually rejected outright as they don't provide the owner with the certainty they need for project planning and budgeting.

Memory Technique

Think 'DART' - Deadline pressure requires quick Adjustment based on Reasonable estimates to protect against major financial Trouble

Reference Hint

Florida Building Construction Standards - Chapter on Bidding Procedures and Contractor Business Practices

More Business & Finance Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing