A scaffold platform is rated for 1,800 pounds. Workers and material total 2,050 pounds. How far over rating is the planned load?
Correct Answer
D) 250 pounds.
The planned load exceeds the rating by 2,050 - 1,800 = 250 pounds.
Why This Is the Correct Answer
The planned load exceeds the rating by 2,050 - 1,800 = 250 pounds.
Why the Other Options Are Wrong
Option A: 150 pounds.
150 pounds. is below the supported result for scaffold safety; it likely omits allowance, conversion, coverage, or final round-up.
Option B: 200 pounds.
200 pounds. is below the supported result for scaffold safety; it likely omits allowance, conversion, coverage, or final round-up.
Option C: 225 pounds.
225 pounds. is below the supported result for scaffold safety; it likely omits allowance, conversion, coverage, or final round-up.
Memory Technique
Measure to planned, adjust for load, then let Checking Loading set the finish line.
Reference Hint
Study anchor (closed-book): memorize Scaffold safety from Cal/OSHA Title 8 Construction Safety Orders; CSLB Law and Business. / Title 8 scaffold load requirements; know the rule or calculation trigger without relying on exam-room lookup.
More Law & Business Questions
A Fresno homeowner wants a $725 cabinet repair and trim adjustment. Which contract step best matches CA home improvement requirements?
A project has $6,500 retainage withheld. The owner releases 60 percent of retainage at substantial completion. How much cash is released?
Cash is $52,500 and monthly burn is $17,500. How many months of runway are available?
A supplier offers 1.5 percent early-pay discount on a $22,000 invoice. What is the discount?
A balance sheet lists assets of $310,000 and liabilities of $185,000. What is owner's equity?
A job is estimated to cost $135,000. What price gives a 25 percent gross margin?
A customer invoice of $4,000 has a stated late charge of 1.5 percent. What late charge is added?
A bid has direct labor of $18,000, materials of $12,500, and equipment rental of $3,500. If the contractor adds 20 percent markup on direct cost, what is the bid price?
A contractor wants a 25 percent gross margin on a job with estimated cost of $60,000. What selling price gives that margin?
A completed project sold for $150,000 and had total cost of $126,000. What gross margin percentage did the project earn?