An IIPP inspection log finds 9 hazards, and 7 are corrected by the follow-up date. How many remain open?
Correct Answer
A) 2 hazards.
Open hazards equal total hazards minus corrected hazards: 9 - 7 = 2.
Why This Is the Correct Answer
Open hazards equal total hazards minus corrected hazards: 9 - 7 = 2.
Why the Other Options Are Wrong
Option B: 7 hazards.
7 hazards. is above the supported result for iipp hazard correction; it likely adds a step the rule does not support.
Option C: 9 hazards.
9 hazards. is above the supported result for iipp hazard correction; it likely adds a step the rule does not support.
Option D: 16 hazards.
16 hazards. is above the supported result for iipp hazard correction; it likely adds a step the rule does not support.
Memory Technique
Name the harm before the guard; inspection, log, finds cannot stand in for Reviewing Corrective-Action.
Reference Hint
Study anchor (closed-book): memorize IIPP hazard correction from Cal/OSHA Title 8 Sections 3203 and 1509; CSLB Law and Business Study. / Title 8 Section 3203 hazard correction; know the rule or calculation trigger without relying on exam-room lookup.
More Law & Business Questions
A Fresno homeowner wants a $725 cabinet repair and trim adjustment. Which contract step best matches CA home improvement requirements?
A project has $6,500 retainage withheld. The owner releases 60 percent of retainage at substantial completion. How much cash is released?
Cash is $52,500 and monthly burn is $17,500. How many months of runway are available?
A supplier offers 1.5 percent early-pay discount on a $22,000 invoice. What is the discount?
A balance sheet lists assets of $310,000 and liabilities of $185,000. What is owner's equity?
A job is estimated to cost $135,000. What price gives a 25 percent gross margin?
A customer invoice of $4,000 has a stated late charge of 1.5 percent. What late charge is added?
A bid has direct labor of $18,000, materials of $12,500, and equipment rental of $3,500. If the contractor adds 20 percent markup on direct cost, what is the bid price?
A contractor wants a 25 percent gross margin on a job with estimated cost of $60,000. What selling price gives that margin?
A completed project sold for $150,000 and had total cost of $126,000. What gross margin percentage did the project earn?
