A crew works 30 working days on a CA project. If toolbox meetings are required at least every 10 working days, what is the minimum number of meetings?
Correct Answer
B) 3 meetings.
At one meeting every 10 working days, 30 working days require 3 meetings.
Why This Is the Correct Answer
At one meeting every 10 working days, 30 working days require 3 meetings.
Why the Other Options Are Wrong
Option A: 2 meetings.
2 meetings. is below the supported result for code of safe practices; it likely omits allowance, conversion, coverage, or final round-up.
Option C: 4 meetings.
4 meetings. is above the supported result for code of safe practices; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Option D: 6 meetings.
6 meetings. is above the supported result for code of safe practices; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Memory Technique
Measure to meeting, adjust for every, then let Planning Tailgate set the finish line.
Reference Hint
Study anchor (closed-book): memorize Code of Safe Practices from Cal/OSHA Title 8 Sections 3203 and 1509; CSLB Law and Business Study. / Title 8 Section 1509 toolbox meetings; know the rule or calculation trigger without relying on exam-room lookup.
More Law & Business Questions
A Fresno homeowner wants a $725 cabinet repair and trim adjustment. Which contract step best matches CA home improvement requirements?
A project has $6,500 retainage withheld. The owner releases 60 percent of retainage at substantial completion. How much cash is released?
Cash is $52,500 and monthly burn is $17,500. How many months of runway are available?
A supplier offers 1.5 percent early-pay discount on a $22,000 invoice. What is the discount?
A balance sheet lists assets of $310,000 and liabilities of $185,000. What is owner's equity?
A job is estimated to cost $135,000. What price gives a 25 percent gross margin?
A customer invoice of $4,000 has a stated late charge of 1.5 percent. What late charge is added?
A bid has direct labor of $18,000, materials of $12,500, and equipment rental of $3,500. If the contractor adds 20 percent markup on direct cost, what is the bid price?
A contractor wants a 25 percent gross margin on a job with estimated cost of $60,000. What selling price gives that margin?
A completed project sold for $150,000 and had total cost of $126,000. What gross margin percentage did the project earn?