A CPR shows an employee name but no rate, hours, or classification. What is the issue?
Correct Answer
A) Incomplete CPR.
Certified payroll must include required payroll details such as rates, hours, and classifications.
Why This Is the Correct Answer
Certified payroll must include required payroll details such as rates, hours, and classifications.
Why the Other Options Are Wrong
Option B: Certified payroll.
Certified payroll. belongs to a different file or record trail; it does not prove the certified payroll records event.
Option C: Tax issue.
Tax issue. belongs to a different file or record trail; it does not prove the certified payroll records event.
Option D: Warranty issue.
Warranty issue. belongs to a different file or record trail; it does not prove the certified payroll records event.
Memory Technique
Certified Payroll proof for Reviewing Shows: event, approval, receipt, follow-up.
Reference Hint
Study anchor (closed-book): memorize Certified payroll records from California Labor Code Sections 1771.4 and 1776; DIR certified payroll. / California Labor Code Section 1776 payroll records; know the rule or calculation trigger without relying on exam-room lookup.
More Law & Business Questions
A Fresno homeowner wants a $725 cabinet repair and trim adjustment. Which contract step best matches CA home improvement requirements?
A project has $6,500 retainage withheld. The owner releases 60 percent of retainage at substantial completion. How much cash is released?
Cash is $52,500 and monthly burn is $17,500. How many months of runway are available?
A supplier offers 1.5 percent early-pay discount on a $22,000 invoice. What is the discount?
A balance sheet lists assets of $310,000 and liabilities of $185,000. What is owner's equity?
A job is estimated to cost $135,000. What price gives a 25 percent gross margin?
A customer invoice of $4,000 has a stated late charge of 1.5 percent. What late charge is added?
A bid has direct labor of $18,000, materials of $12,500, and equipment rental of $3,500. If the contractor adds 20 percent markup on direct cost, what is the bid price?
A contractor wants a 25 percent gross margin on a job with estimated cost of $60,000. What selling price gives that margin?
A completed project sold for $150,000 and had total cost of $126,000. What gross margin percentage did the project earn?